4
DU
Demo userProduction planner
Work order 1103
QASA2007 Base frame × 5 · Mechanical assembly · due 13 Oct · est 75 min · printed
Entered
Allocated
Issued
In progress
QA
Complete
Units (5 / 5)
| Serial | Result | Reason | Test report | |
|---|---|---|---|---|
| SA2007-0008 | Pass | |||
| SA2007-0009 | Pass | Failed pressure test | ||
| SA2007-0010 | Pass | |||
| SA2007-0011 | Pass | |||
| SA2007-0012 | Pass |
Record a defect
Waste a part or a whole unit against this build. The cost is taken from the part, or the product's cost to manufacture.
Awaiting team leader QA sign-off
Check the sampled units and visual finish, then approve or send back.