4
DU
Demo userProduction planner
TP-100-SA2004-0016
FAILSA2004 Valve block · Serial SA2004-0016 · 08 Oct 2026
Summary
Procedure TP-10013 of 14 steps passed · 1 failed
Comments
No comments recorded.
1. Documentation
2 steps| Step | Criteria | Result | Sign-off |
|---|---|---|---|
| 1.1 | Latest drawings and test sheet to hand | PASS | JO |
| 1.2 | Test equipment in calibration | PASS | JO |
2. Visual inspection
2 steps| Step | Criteria | Result | Sign-off |
|---|---|---|---|
| 2.1 | No physical damage; labels legible | PASS | JO |
| 2.2 | All fixings tight and wires labelled | PASS | JO |
3. Dead testing
3 steps| Step | Criteria | Result | Sign-off |
|---|---|---|---|
| 3.1 | Supply disconnected; no indicators lit | PASS | JO |
| 3.2 | Continuity of all wiring confirmed | PASS | JO |
| 3.3 | Insulation resistance within limits | PASS | JO |
4. Power-up
2 steps| Step | Criteria | Result | Sign-off |
|---|---|---|---|
| 4.1 | Supply on; status indicators correct Note: Loose terminal on X2 |
FAIL | JO |
| 4.2 | Controller boots without faults | PASS | JO |
5. Functional test
3 steps| Step | Criteria | Result | Sign-off |
|---|---|---|---|
| 5.1 | All inputs respond as drawn | PASS | JO |
| 5.2 | All outputs operate correctly | PASS | JO |
| 5.3 | Emergency stop and reset work | PASS | JO |
6. Sign-off
2 steps| Step | Criteria | Result | Sign-off |
|---|---|---|---|
| 6.1 | Comments recorded | PASS | JO |
| 6.2 | Test sheet signed | PASS | JO |