TP-100-SA2004-0016

FAIL

SA2004 Valve block · Serial SA2004-0016 · 08 Oct 2026

Summary

Procedure TP-100
Tested by
Jordan
Date
08 Oct 2026
Work order
1082
13 of 14 steps passed · 1 failed

Comments

No comments recorded.

1. Documentation

2 steps
StepCriteriaResultSign-off
1.1 Latest drawings and test sheet to hand PASS JO
1.2 Test equipment in calibration PASS JO

2. Visual inspection

2 steps
StepCriteriaResultSign-off
2.1 No physical damage; labels legible PASS JO
2.2 All fixings tight and wires labelled PASS JO

3. Dead testing

3 steps
StepCriteriaResultSign-off
3.1 Supply disconnected; no indicators lit PASS JO
3.2 Continuity of all wiring confirmed PASS JO
3.3 Insulation resistance within limits PASS JO

4. Power-up

2 steps
StepCriteriaResultSign-off
4.1 Supply on; status indicators correct
Note: Loose terminal on X2
FAIL JO
4.2 Controller boots without faults PASS JO

5. Functional test

3 steps
StepCriteriaResultSign-off
5.1 All inputs respond as drawn PASS JO
5.2 All outputs operate correctly PASS JO
5.3 Emergency stop and reset work PASS JO

6. Sign-off

2 steps
StepCriteriaResultSign-off
6.1 Comments recorded PASS JO
6.2 Test sheet signed PASS JO